  1. The Contractor shall mark out the proposed pipe route at 10m intervals and shall obtain the Engineer's approval for it before beginning trenchless construction.
  2. Unless unforeseen obstructions are encountered, the pipeline shall be installed in straight runs or smooth curves as shown on the approved drawings.
  3. All pipelines installed using trenchless technology shall include tracer wire.