Infrastructure Development Code

PreviousNext

  1. Where the reused material is to be subsequently overlaid with basecourse it shall be shaped and compacted such that it meets the profile on the approved drawings to a tolerance of plus 0mm to minus 20mm.
  2. Where imported basecourse is to be overlaid, the reused material shall be compacted and shaped before the placement of the imported basecourse.
  3. The basecourse construction, whether imported or reused material, shall conform to the specification for basecourse construction given in CS-15.3 Basecourse Layer.
  4. All surfacing material shall be removed from the site and legally disposed of by the Contractor.

Definitions in this section

Approved drawings

Contractor