Search
× Search
Menu
  1. Home
  2. General
  3. Infrastructure Development Processes
  4. Quality Assurance Information Requirements
    1. QA-1 Resource Consent Application Requirements
    2. QA-2 Works Undertaken By or For a Council
    3. QA-3 Development Works Approval
    4. QA-4 Survey Plan (s223) Approval
    5. QA-5 Final Sign Off (s224c) Application Requirements
    6. QA-6 As-Built Information
    7. QA-7 Bonds and Maintenance Fee
    8. QA-8 Building Consent Considerations
  5. Design Standards
    1. DS-1 General Provisions
    2. DS-2 Streetscape
    3. DS-3 Reserves
    4. DS-4 Transportation Network
    5. DS-5 Stormwater
    6. DS-6 Wastewater
    7. DS-7 Water Supply
    8. DS-8 Public Lighting
    9. DS-9 Network Utilities
    10. DS-10 Natural Hazards & Earthworks
    11. DS-11 Road Zone/Road Reserve Occupancy
    12. DS-12 Building Consent Considerations
  6. Standard Drawings
    1. SD-1 General Provisions
    2. Street design diagrams
    3. T100 Perspective Drawings
    4. T200 Streetscape
    5. T300 Reserves
    6. T400 Transport Network
    7. T500 Stormwater
    8. T600 Wastewater
    9. T700 Water Supply
    10. T800 Public Lighting
    11. AB As-Built Drawings
  7. Approved Materials
  8. Construction Standards
    1. CS-1 General
    2. CS-2 Site Clearance
    3. CS-3 Earthworks
    4. CS-4 Excavation
    5. CS-5 Excavation in Trench
    6. CS-6 Fill
    7. CS-7 Bedding & Backfill
    8. CS-8 Subsoil Drainage for Earthworks & Roads
    9. CS-9 Pipework
    10. CS-10 Pipe Fittings
    11. CS-11 Manholes & Rodding Eyes
    12. CS-12 Sumps
    13. CS-13 Trenchless Technology
    14. CS-14 Road Ripping
    15. CS-15 Road Pavement Layers
    16. CS-16 Kerb & Channel
    17. CS-17 Concrete Work
    18. CS-18 Carriageway Surfacing
    19. CS-19 Roadmarking
    20. CS-20 Berm Features
    21. CS-21 Street Structures
    22. CS-22 Road Maintenance
    23. CS-23 Grassing & Turfing
    24. CS-24 Vegetation Planting & Gardens
    25. CS-25 Reinstatement
  9. Inspection & Testing Requirements
    1. IT-1 General Provision
    2. IT-2 Streetscape
    3. IT-3 Reserves
    4. IT-4 Transportation Network
    5. IT-5 Stormwater
    6. IT-6 Wastewater
    7. IT-7 Water Supply
    8. IT-8 Public Lighting
    9. IT-9 Network Utilities
Infrastructure Development Code

DS-1.14 Managing Earthworks

PreviousNext

Earthworks for subdivision and building platforms can have substantial and cumulative effects on the aquatic receiving environment, silting streams and estuaries, and altering catchments. Earthworks can significantly alter topography, which otherwise adds to the local character and identity of the subdivision.

Earthworks are often a considerable expense to the developer and can have adverse effects if poorly managed. Preferred design solutions limit the extent of earthworks, reduce erosion and sedimentation, and retain the site’s natural features.

DS-1.14.1   Design Elements

The following shall be considered during the design process:

  1. Limiting the earthworks (volume and area). Avoid disturbing the natural landform and steep slopes and thus adverse effects on aquatic environments. Excavate only the areas required for building platforms and access.
  2. Designing the layout of roads and lots to work with the natural form of the site.
  3. Retaining the site’s topsoil, allowing the landscape to develop with new dwellings and avoiding the need to dispose large volumes of spoil.

Definitions in this section

Design

Developer

Lot

Road