Search
× Search
Menu
  1. Home
  2. General
  3. Infrastructure Development Processes
  4. Quality Assurance Information Requirements
    1. QA-1 Resource Consent Application Requirements
    2. QA-2 Works Undertaken By or For a Council
    3. QA-3 Development Works Approval
    4. QA-4 Survey Plan (s223) Approval
    5. QA-5 Final Sign Off (s224c) Application Requirements
    6. QA-6 As-Built Information
    7. QA-7 Bonds and Maintenance Fee
    8. QA-8 Building Consent Considerations
  5. Design Standards
    1. DS-1 General Provisions
    2. DS-2 Streetscape
    3. DS-3 Reserves
    4. DS-4 Transportation Network
    5. DS-5 Stormwater
    6. DS-6 Wastewater
    7. DS-7 Water Supply
    8. DS-8 Public Lighting
    9. DS-9 Network Utilities
    10. DS-10 Natural Hazards & Earthworks
    11. DS-11 Road Zone/Road Reserve Occupancy
    12. DS-12 Building Consent Considerations
  6. Standard Drawings
    1. SD-1 General Provisions
    2. Street design diagrams
    3. T100 Perspective Drawings
    4. T200 Streetscape
    5. T300 Reserves
    6. T400 Transport Network
    7. T500 Stormwater
    8. T600 Wastewater
    9. T700 Water Supply
    10. T800 Public Lighting
    11. AB As-Built Drawings
  7. Approved Materials
  8. Construction Standards
    1. CS-1 General
    2. CS-2 Site Clearance
    3. CS-3 Earthworks
    4. CS-4 Excavation
    5. CS-5 Excavation in Trench
    6. CS-6 Fill
    7. CS-7 Bedding & Backfill
    8. CS-8 Subsoil Drainage for Earthworks & Roads
    9. CS-9 Pipework
    10. CS-10 Pipe Fittings
    11. CS-11 Manholes & Rodding Eyes
    12. CS-12 Sumps
    13. CS-13 Trenchless Technology
    14. CS-14 Road Ripping
    15. CS-15 Road Pavement Layers
    16. CS-16 Kerb & Channel
    17. CS-17 Concrete Work
    18. CS-18 Carriageway Surfacing
    19. CS-19 Roadmarking
    20. CS-20 Berm Features
    21. CS-21 Street Structures
    22. CS-22 Road Maintenance
    23. CS-23 Grassing & Turfing
    24. CS-24 Vegetation Planting & Gardens
    25. CS-25 Reinstatement
  9. Inspection & Testing Requirements
    1. IT-1 General Provision
    2. IT-2 Streetscape
    3. IT-3 Reserves
    4. IT-4 Transportation Network
    5. IT-5 Stormwater
    6. IT-6 Wastewater
    7. IT-7 Water Supply
    8. IT-8 Public Lighting
    9. IT-9 Network Utilities
Infrastructure Development Code

CS-13.8 Tolerances

PreviousNext

The following tolerances shall apply to trenchless construction:

  1. Invert Levels

The permissible deviation from the designated level of the invert at each manhole or structure shall be ±50mm, provided that the fall between successive manholes or structures shall be at least 90% of that specified.

  1. Horizontal Alignment

The permissible deviation of the horizontal alignment between manholes or structures shall be ±100mm.

  1. Gradient

For straight gradients, the permissible deviation from the specified gradient shall be ±50mm from a straight line drawn between the inverts of successive manholes, provided that no point in the pipeline is lower than any downstream point.  For curved gradients, the curvature shall be in the direction of the specified curvature and no point in the pipeline shall be lower than any downstream point.

    Directional drilling only:
    Annulus:            0 – 25mm between slurry and hole
    Back ream diameter:    Pipe diameter + 25% minimum, + 50% maximum

 