Search
× Search
Menu
  1. Home
  2. General
  3. Infrastructure Development Processes
  4. Quality Assurance Information Requirements
    1. QA-1 Resource Consent Application Requirements
    2. QA-2 Works Undertaken By or For a Council
    3. QA-3 Development Works Approval
    4. QA-4 Survey Plan (s223) Approval
    5. QA-5 Final Sign Off (s224c) Application Requirements
    6. QA-6 As-Built Information
    7. QA-7 Bonds and Maintenance Fee
    8. QA-8 Building Consent Considerations
  5. Design Standards
    1. DS-1 General Provisions
    2. DS-2 Streetscape
    3. DS-3 Reserves
    4. DS-4 Transportation Network
    5. DS-5 Stormwater
    6. DS-6 Wastewater
    7. DS-7 Water Supply
    8. DS-8 Public Lighting
    9. DS-9 Network Utilities
    10. DS-10 Natural Hazards & Earthworks
    11. DS-11 Road Zone/Road Reserve Occupancy
    12. DS-12 Building Consent Considerations
  6. Standard Drawings
    1. SD-1 General Provisions
    2. Street design diagrams
    3. T100 Perspective Drawings
    4. T200 Streetscape
    5. T300 Reserves
    6. T400 Transport Network
    7. T500 Stormwater
    8. T600 Wastewater
    9. T700 Water Supply
    10. T800 Public Lighting
    11. AB As-Built Drawings
  7. Approved Materials
  8. Construction Standards
    1. CS-1 General
    2. CS-2 Site Clearance
    3. CS-3 Earthworks
    4. CS-4 Excavation
    5. CS-5 Excavation in Trench
    6. CS-6 Fill
    7. CS-7 Bedding & Backfill
    8. CS-8 Subsoil Drainage for Earthworks & Roads
    9. CS-9 Pipework
    10. CS-10 Pipe Fittings
    11. CS-11 Manholes & Rodding Eyes
    12. CS-12 Sumps
    13. CS-13 Trenchless Technology
    14. CS-14 Road Ripping
    15. CS-15 Road Pavement Layers
    16. CS-16 Kerb & Channel
    17. CS-17 Concrete Work
    18. CS-18 Carriageway Surfacing
    19. CS-19 Roadmarking
    20. CS-20 Berm Features
    21. CS-21 Street Structures
    22. CS-22 Road Maintenance
    23. CS-23 Grassing & Turfing
    24. CS-24 Vegetation Planting & Gardens
    25. CS-25 Reinstatement
  9. Inspection & Testing Requirements
    1. IT-1 General Provision
    2. IT-2 Streetscape
    3. IT-3 Reserves
    4. IT-4 Transportation Network
    5. IT-5 Stormwater
    6. IT-6 Wastewater
    7. IT-7 Water Supply
    8. IT-8 Public Lighting
    9. IT-9 Network Utilities
Infrastructure Development Code

CS-23.1 Preparation for Sowing or Turfing

PreviousNext

  1. Fertilising and grassing shall be carried out over all existing grassed areas disturbed by contract activity and other specified areas which may require reinstatement. In existing grassed areas, excessive compaction of the subsoil shall be relieved by subsoiling or similar as required to achieve satisfactory long term growing conditions.
  2. All topsoil removed to permit development or contract works to be carried out shall be stockpiled for reuse.
  3. All new grass areas shall be built on subgrades prepared to a California Bearing Ratio (CBR) of not less than 5 and no greater than 7. A minimum 100mm layer of clean, friable peat loam or sandy loam topsoil free of all perennial weeds, stones and rubbish shall be placed on the subgrade. If the subgrade has been backfilled with sand or if the existing subgrade material is of a sandy nature then the 100mm topsoil shall be of a heavier silt loam.
  4. Perennial weeds shall be sprayed according to manufacturer’s instructions and at least 14 days before cultivation with Glyphosate plus Versatil, if clover, thistles, etc. are a problem. All stones, rubbish and foreign materials shall be removed from the areas to be grassed and the whole area rotary hoed to the depth of the topsoil or 150mm whichever is the lesser.

Definitions in this section

Contract works

 