Slips of material from cut batters or natural ground shall be removed and disposed of as specified. Slips with an in-place volume exceeding 10m³ will be paid for at the appropriate scheduled rate or amount for excavation, provided such slips did not result from any foreseeable action or inaction by the Contractor.