Search
× Search
Menu
  1. Home
  2. General
  3. Infrastructure Development Processes
  4. Quality Assurance Information Requirements
    1. QA-1 Resource Consent Application Requirements
    2. QA-2 Works Undertaken By or For a Council
    3. QA-3 Development Works Approval
    4. QA-4 Survey Plan (s223) Approval
    5. QA-5 Final Sign Off (s224c) Application Requirements
    6. QA-6 As-Built Information
    7. QA-7 Bonds and Maintenance Fee
    8. QA-8 Building Consent Considerations
  5. Design Standards
    1. DS-1 General Provisions
    2. DS-2 Streetscape
    3. DS-3 Reserves
    4. DS-4 Transportation Network
    5. DS-5 Stormwater
    6. DS-6 Wastewater
    7. DS-7 Water Supply
    8. DS-8 Public Lighting
    9. DS-9 Network Utilities
    10. DS-10 Natural Hazards & Earthworks
    11. DS-11 Road Zone/Road Reserve Occupancy
    12. DS-12 Building Consent Considerations
  6. Standard Drawings
    1. SD-1 General Provisions
    2. Street design diagrams
    3. T100 Perspective Drawings
    4. T200 Streetscape
    5. T300 Reserves
    6. T400 Transport Network
    7. T500 Stormwater
    8. T600 Wastewater
    9. T700 Water Supply
    10. T800 Public Lighting
    11. AB As-Built Drawings
  7. Approved Materials
  8. Construction Standards
    1. CS-1 General
    2. CS-2 Site Clearance
    3. CS-3 Earthworks
    4. CS-4 Excavation
    5. CS-5 Excavation in Trench
    6. CS-6 Fill
    7. CS-7 Bedding & Backfill
    8. CS-8 Subsoil Drainage for Earthworks & Roads
    9. CS-9 Pipework
    10. CS-10 Pipe Fittings
    11. CS-11 Manholes & Rodding Eyes
    12. CS-12 Sumps
    13. CS-13 Trenchless Technology
    14. CS-14 Road Ripping
    15. CS-15 Road Pavement Layers
    16. CS-16 Kerb & Channel
    17. CS-17 Concrete Work
    18. CS-18 Carriageway Surfacing
    19. CS-19 Roadmarking
    20. CS-20 Berm Features
    21. CS-21 Street Structures
    22. CS-22 Road Maintenance
    23. CS-23 Grassing & Turfing
    24. CS-24 Vegetation Planting & Gardens
    25. CS-25 Reinstatement
  9. Inspection & Testing Requirements
    1. IT-1 General Provision
    2. IT-2 Streetscape
    3. IT-3 Reserves
    4. IT-4 Transportation Network
    5. IT-5 Stormwater
    6. IT-6 Wastewater
    7. IT-7 Water Supply
    8. IT-8 Public Lighting
    9. IT-9 Network Utilities
Infrastructure Development Code

CS-7.0 Bedding and Backfill

PreviousNext

Pipes shall be bedded and protected as shown the approved drawings. Where not specified, bedding and protection shall be in accordance with the particular manufacturer’s specifications. There shall be no sharp stones or large clay lumps in the bedding or surround. 

In public areas, backfilling shall keep pace with the laying of pipes so that there is no more than 20m of open trench at any time.
Care shall be taken during backfilling to prevent displacement of the laid pipes. 

The Contractor shall reinstate trenches within 7 days of back fill completion unless agreed otherwise by the Engineer. The surface level of the reinstated trench shall match the surrounding surface level.


Definitions in this section

Approved drawings

Contractor

Engineer